June 6, 2014
Chasselton Residents
Dear Residents:
Please be advised the roof on your building is scheduled for replacement (weather permitting) beginning on Monday, June 16, 2014, continuing until they are finished. Fisher Roofing will be performing the work.
There may be limited parking availability around the building due to equipment.
You will want to be aware of work areas and drop zones as you enter and leave the building.
Please contact Nick McIntyre (nick@bluecommunity.com) at Blue Mountain Community Management if you have any questions.
Thank you for your patience during this needed building upgrade.
Sincerely,
Blue Mountain Community Management
UPDATE: Fisher Roofing is planning to begin staging, roof tear off, and installation at 8AM Wednesday 6/18 and continuing through Friday 6/20. The roofing project will continue Monday – Wednesday 6/23 – 6/25.